Question: #2) Following information is available about a project. Activity Activity Time (Weeks) 5 Immediate Predecessor(s) a b 4 3 a d 4 a e 6

#2) Following information is available about a

#2) Following information is available about a project. Activity Activity Time (Weeks) 5 Immediate Predecessor(s) a b 4 3 a d 4 a e 6 a f 4 b, c 5 d h 6 d, e 6 f 4 g, h A critical resource used by activities "b", "c", "d" and "e" is scarce. To which activity would you assign the specific resource first, for the following? (5 points) Note: For each priority rule (below) you have to select one activity (b, c, d, or e). i. ii. iii. Minimum slack first rule Most followers (successors) rule Most critical followers rule