Question: 1 - Given the following network: a) Find the earliest time the project will be completed. b) Find the critical path c) If activity I

1 - Given the following network: a) Find the
1 - Given the following network: a) Find the earliest time the project will be completed. b) Find the critical path c) If activity I is delayed by 5 days find the completion time of the entire project. Activity t G A E 200 D 8 6 11 6 7 11 12 G I H I 10 10 2 - A food processor company uses approximately 10 glass jars a week for its fruit juice product. Monthly holding cost is $0.10 per jar, and ordering cost is $40 per order Find optimal order quantity htharder O-2007