Question: 1. Given the information in the table below, answer the following questions: Activity Duration (in days) Predecessor A 4 B 6 4 D 3 A

1. Given the information in the table below,

1. Given the information in the table below, answer the following questions: Activity Duration (in days) Predecessor A 4 B 6 4 D 3 A E 5 B F 1 B 7 C . 2 D, E 1 4 G J 2 H, F, un G a. Construct the network diagram in two formats - AOA and AON (10 pts) b. Determine each activity's ES, EF, LS, LF and slack (25 pts) C. Determine all alternative paths and their respective duration time (10 pts) d. What is the critical path and critical time (5 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!