Question: 1) Given this cumulative data, taken from the Integrated Program Management Report, what is the estimate at completion (EAC), using the cost performance index (CPI)

1) Given this cumulative data, taken from the Integrated Program Management Report, what is the estimate at completion (EAC), using the cost performance index (CPI) as the performance factor for the Cooling System Work Breakdown Structure (WBS) element? (Note: use 3 decimal places on all interim calculations)
(IMAGE DESCRIPTION: WBS number 1.1.3.10, Cooling System, has a BCWS of 1830, a BCWP of 1444, an ACWP of 1973, a BAC of 2291, and an EAC of 2706.)
A.) 3438.4
B.) 3045.4
C.) 3130.1
D.) 1157.1
 1) Given this cumulative data, taken from the Integrated Program Management

WBS Number 1.1.3.10 Cooling System Description BCWS BCWP ACWP BAC ??? EAC 1830 1444 1973 2291 2706

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!