Question: Given this cumulative data, taken from the Integrated Program Management Report, what is the estimate at completion (EAC), using the cost performance index (CPI) as
| Given this cumulative data, taken from the Integrated Program Management Report, what is the estimate at completion (EAC), using the cost performance index (CPI) as the performance factor for the Cooling System Work Breakdown Structure (WBS) element? (Note: use 3 decimal places on all interim calculations) (IMAGE DESCRIPTION: WBS number 1.1.3.10, Cooling System, has a BCWS of 1830, a BCWP of 1444, an ACWP of 1973, a BAC of 2291, and an EAC of 2706.) |
| 3045.4 |
| 1157.1 |
| 3438.4 |
3130.1 |