Question: 1- Level the resources (Work force) such that the maximum number of workers in any day not to exceed 8 workers. 2- What is the

1- Level the resources (Work force) such that the

1- Level the resources (Work force) such that the maximum number of workers in any day not to exceed 8 workers. 2- What is the optimum number of workers for this project? Activity I.P.A Activity I.P.A F D B G E H C, F, G D A, B 1 G C E B Finish HI Normal Number of Workers Number of workers Activity Duration Normal Minimum A 3 4 2 B 5 4 2 6 5 3 D 5 3 1 E 3 2 1 F 5 4 2 G 3 2 2 | 3 3 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!