Question: I.P.A. = Immediate Precedence Activity 1- Level the resources (Work force) such that the maximum number of workers in any day not to exceed 8

I.P.A. = Immediate Precedence Activity
1- Level the resources (Work force) such that the maximum number of workers in any day not to exceed 8 workers. 2- What is the optimum number of workers for this project? Activity 1.P.A Activity I.P.A A F D B G E C . C, F, G D A, B 1 G. C E Finish H1 Normal Number of Workers Number of workers Activity Duration Normal Minimum A 3 4 2 B 5 4 2 C 16 5 3 D 5 3 1 E 3 2 1 F 5 4 2 G 3 3 2 H 2 3 3 3 3 2Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
