Question: 1. Leveling outside slack _________ results in increased project duration. a) Always b) Never c) Sometimes 2. Even with a positive value of schedule variance
1. Leveling outside slack _________ results in increased project duration.
a) Always
b) Never
c) Sometimes
2. Even with a positive value of schedule variance index (SV), a project could be behind or delayed in terms of completion date. Discuss how that could be possible. Please provide a detailed scenario based answer.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts