Question: 1 . Perform logical compression to calculate the normal, least - cost , and crash durations for the following project. Also, calculate the cost associated

1. Perform logical compression to calculate the normal, least-cost, and crash durations for the
following project. Also, calculate the cost associated with each duration. Indirect costs are
$100 per day. Use the end of day convention.
Activity Predecessors
Duration (Days Cost ($)
Normal Crash Normal Crash
A -75500640
B A 65550630
C A 85800935
D B 1071,2001,440
E B, C 64600700
F C 43500590
G D, F 427001,000
H E, F 74650950
I G, H 22300300