Question: 1 point Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To

1 point
Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity should be crashed first, adding to project cost.
Activity Normal Time Normal Cost Crash Time Crash Cost
\table[[One,8 days,$6,000,7 days,$6,800