Question: Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one
Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
| Activity | Normal Time | Normal Cost | Crash Time | Crash Cost |
| One | 8 days | $6,000 | 7 days | $6,800 |
| Two | 10 days | $4,000 | 8 days | $5,000 |
A.
One; $800
B.
Two; $500
C.
Two; $5,000
D.
One; $6,800
E.
One or Two should be crashed; $1,300