Question: Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one

Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.

Activity

Normal Time

Normal Cost

Crash Time

Crash Cost

One

8 days

$6,000

7 days

$6,800

Two

10 days

$4,000

8 days

$5,000

A.

One; $800

B.

Two; $500

C.

Two; $5,000

D.

One; $6,800

E.

One or Two should be crashed; $1,300