Question: Two activities on the same critical path are candidates for crashing on a CPM network Activity details are in the table below. To cut one

Two activities on the same critical path are
Two activities on the same critical path are candidates for crashing on a CPM network Activity details are in the table below. To cut one day from the project's duration, activity should be crashed first, adding to project cost Crash Time 7 days 8 days Crash Cost SG 800 $5000 Activity Normal Time Normal Cost One 8 days $6.000 Two 10 days $4,000 One: 56.800 One: $800 Two: $500 Two: $5.000 One or Two should be crashed: $1,300