Question: 1. Project E Data Task Duration (Days) Predecessor(s) $Budget Status at the end of day 23 K 8 Start 6,000 Completed and spent 5,000 D

1. Project E Data Task Duration (Days) Predecessor(s) $Budget Status at the end of day 23 K 8 Start 6,000 Completed and spent 5,000 D 6 K(SS+2) 3,000 Completed and spent 2,000 B 10 K , D(FS+3) 4,000 C