Question: Project ' D ' ?data: Task Duration ( days ) Predecessors Budget Status at the end of day 2 5 R 8 Start 5 ,

Project ' D ' ?data:
Task
Duration ( days )
Predecessors
Budget
Status at the end of day 2 5
R
8
Start
5 , 0 0 0
Completed and spent $ 5 , 0 0 0
S
3
R ( FS + 2 )
3 , 0 0 0
Completed and spent $ 2 , 0 0 0
5
S ( SS + 1 0 )
6 , 0 0 0
Half done and spent $ 2 , 5 0 0
R , ?T ( FF )
7 , 0 0 0
Not started and spent $ 1 0 0
E
4
C ( SF + 2 )
4 , 0 0 0
8 0 % ?done and spent
$ 2 , 5 0 0
3
T ( FF + 7 )
2 , 0 0 0
3 0 % ?done and spent
$ 1 , 2 0 0
F
7
7 , 0 0 0
Not started
End
F
Use Base 1 ?to develop an AON network diagram and a Gantt Chart
The status date is the end of day 2 5 .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!