Question: 1 pts Bellow we have the expected time and Standard Deviation of the activities for a project. Activity Standard Deviation Expected Time 12 A 4

1 pts Bellow we have the expected time and
1 pts Bellow we have the expected time and Standard Deviation of the activities for a project. Activity Standard Deviation Expected Time 12 A 4 B 11 4 14 4 D 9 3 E 3 1 The critical path of this project is A-B-C-e. What is the expected completion time and Standard Deviation of the project? 49.16 40.7 49.13 40.13

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!