Question: Question 35 Bellow we have the expected time and Standard Deviation of the activities for a project. Activity Expected Time Standard Deviation A 12 4

Question 35 Bellow we have the expected time and
Question 35 Bellow we have the expected time and Standard Deviation of the activities for a project. Activity Expected Time Standard Deviation A 12 4 B 11 4 14 4 D 9 3 E 3 1 The critical path of this project is A-B-C-E. What is the expected completion time and Standard Deviation of the project? 40,13 49, 16 40,7 49.13