Question: 1 . Question 1 A project manager creates a timeline and defines all tasks that the team needs to complete. What phase of the project
Question
A project manager creates a timeline and defines all tasks that the team needs to complete. What phase of the project life cycle are they implementing?
point
Making a plan
Close the project
Execute and complete tasks
Initiate the project
Step by Step Solution