Question: 1. Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Immediate Predecessors B D

1. Task time estimates for the modification of an
1. Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Immediate Predecessors B D E F G Time (in hours) 6 7 5 8 5 8 4 A B, C B,C D EF a. Draw the project network using AON. b. Identify the critical path. C. What is the expected project length? d. Draw a gantt chart for the project