1. The following table refers to a building project.
Activity Duration (months) Predecessors
A 7 None
B 10 None
C 7 B
D 8 A
E 6 A
F 5 E
G 10 C, D, F
H 11 E
I 2 G,H
. Identify the critical path, its duration and the activity slacks