Question: 1. The project completion time would be delayed by 2 days 2. The project completion time would be shortened by 2 days 3. We would

1. The project completion time would be delayed by 2 days
2. The project completion time would be shortened by 2 days
3. We would have 2 critical paths in the project
4. The project completion time would be unaffected
Given the project network shown below, A E what would be the impact of a delay of 2 days in activity EStep by Step Solution