Question: Given the project network shown below, what would be the impact of a delay of 2 days in activity E? We would have 2 critical

Given the project network shown below, what would

Given the project network shown below, what would be the impact of a delay of 2 days in activity E? We would have 2 critical paths in the project The project completion time would be delayed by 2 days The project completion time would be shortened by 2 days The project completion time would be unaffected