Question: 1. The project duration is: * 25 None 22 16 2. The slack time of activity E is: * None 0 9 8 3. The

1. The project duration is: * 25 None 22 16
2. The slack time of activity E is: * None 0 9 8
3. The slack time of activity F is: * None 8 2 0
4. The CP contains: * C, F, H A, D, G None B, E, G
5. The duration of activity A is: * 8 5 9 None
6. The variance of activity C is: * 2.7 1 None 1.7
7. The project standard deviation is: (Take one number after the comma) * 1 1.8 2.6 None
8. What is the probability to finish the project before 25 weeks: * none 95.15% 92.2% 90.2%
A network consists of the following list. Times are given in weeks. Preceding Most Pessimis 16 Activity A B D E F G H A B, C D, E, F F Optimistic 6 2 3 4 2 6 3 4 8 4 3 8 5 10 5 6 6 9 12 8 14 7 8Step by Step Solution