Question: CH 3 . PROJECT MANAGEMENT 3 . 5 The table below shows the activities, immediate predecessors, and activity durations of a project. Draw the AON

CH3. PROJECT MANAGEMENT
3.5 The table below shows the activities, immediate predecessors, and activity durations of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path?
\table[[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],\table[[DURATION],[(DAYS)]]],[A,-,2],[B,A,4],[C,A,4],[D,B,6],[E,D,9],[F,C,8],[G,E. F,2],[H,G,2],[I,G,3],[J,H. I,4],[K,J,4]]
CH 3 . PROJECT MANAGEMENT 3 . 5 The table below

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!