Question: CH 3 . PROJECT MANAGEMENT 3 . 5 The table below shows the activities, immediate predecessors, and activity durations of a project. Draw the AON
CH PROJECT MANAGEMENT
The table below shows the activities, immediate predecessors, and activity durations of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path?
tableACTIVITYtableIMMEDIATEPREDECESSORStableDURATIONDAYSABACADBEDFCGE FHGIGJH I,KJ