Question: The table below shows the activities, immediate predecessors, and activity durations of a project. Draw AON project network . How long would it take to
- The table below shows the activities, immediate predecessors, and activity durations of a project. Draw AON project network . How long would it take to complete this project? What is the length of the critical path?
| ACTIVITY | IMMEDIATE PREDECESSOR(S) | DURATION (DAYS0 |
| A | - | 2 |
| B | A | 4 |
| C | A | 4 |
| D | B | 6 |
| E | D | 9 |
| F | C | 8 |
| G | E,F | 2 |
| H | G | 2 |
| I | G | 3 |
| J | H,I | 4 |
| K | J | 4 |