Question: The table below shows the activities, immediate predecessors, and activity durations of a project. Draw AON project network . How long would it take to

  1. The table below shows the activities, immediate predecessors, and activity durations of a project. Draw AON project network . How long would it take to complete this project? What is the length of the critical path?

ACTIVITY

IMMEDIATE

PREDECESSOR(S)

DURATION

(DAYS0

A

-

2

B

A

4

C

A

4

D

B

6

E

D

9

F

C

8

G

E,F

2

H

G

2

I

G

3

J

H,I

4

K

J

4