Question: Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete
Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path? Calculate the slack time and total duration of the project
Activity Immediate Predecessor(s) Time (Days)
A - 2
B A 3
C A 4
D B 6
E D 9
F C 8
G E, F 2
H G 2
I G 3
J H, I 4
K J 4