Question: Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete

Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path? Calculate the slack time and total duration of the project

Activity Immediate Predecessor(s) Time (Days)

A - 2

B A 3

C A 4

D B 6

E D 9

F C 8

G E, F 2

H G 2

I G 3

J H, I 4

K J 4

Note: The answer must be in an organized manner

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!