Question: 1. The table below shows the data for a project scheduled to start on Monday, 12/07/20. Use Microsoft Project to create a project plan, including
1. The table below shows the data for a project scheduled to start on Monday, 12/07/20. Use Microsoft Project to create a project plan, including WBS, for this project. Inspect the resulting network diagram, and make sure there are no 'dangling ends'. Use the Project Summary Task feature to determine the project duration assuming there is no overtime or work on weekends. Create a Resource Sheet and assign the required workers to each activity. If a total of 8 workers are available, rearrange the timing of project activities to minimize instances of resource over- allocation without extending the project duration (15 points) Activity Duration Immediate Workers (Days) Predecessor A 12 4 B 1 C B 3 D 6 AC 2 E 10 F DE 2 . 6 8 B 4 4