Question: 1. This can be calculated by dividing the available time for production by the number of units needed. Group of answer choices -Cycle -Takt -Lead
1. This can be calculated by dividing the available time for production by the number of units needed. Group of answer choices
-Cycle
-Takt
-Lead
-Variable
2.
Daily demand is 10,000 units. Lead time is 15 days. What is the Reorder Point (ROP)?
-10,000
-867
-150,000
-667
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts