Question: 1 Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months,

1
1 Using PERT, Adam Munson was able to determine
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 9. a) The probability that the project will be completed in 15 months = round your response to four decimal places). b) The probability that the project will be completed in 23 months = (round your response to four decimal places). c) The probability that the project will be completed in 27 months = round your response to four decimal places). d) The probability that the project will be completed in 33 months = round your response to four decimal places). .) The due date that yields a 95% chance of completion = | months (round your response to two decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!