Question: 1. When would a task in Project NOT use effort-driven scheduling? Select an answer: when the units change as you add or remove resources when

1. When would a task in Project NOT use effort-driven scheduling? Select an answer: when the units change as you add or remove resources when the work increases or decreases as you add or remove resources when the duration changes as you add or remove resources when the resources increase as you add or remove work