Question: 1. Which items are inputs to the estimate costs process? Select one or more: a. Enterprise environmental factors b. Policy for cost contingencies c. Risk

1. Which items are inputs to the estimate costs process?

Select one or more:

a. Enterprise environmental factors

b. Policy for cost contingencies

c. Risk register

d. Variance thresholds

e. Organizational process assets

2. A project's BAC is $65,000. Its EV is $58,000 and its AC is $60,000. The cumulative CPI is 0.97 and the cumulative SPI is 1.23. The bottom-up ETC is $6,500.

What is the bottom-up EAC for the project?

Select one:

a. $67,000

b. $66,500

c. $65,882.35

d. $67,010.31