Question: 1 . Who is responsible for project integration? Project team Project manager Project stakeholders Project sponsor 2 . Which element ( s ) of the
Who is responsible for project integration?
Project team
Project manager
Project stakeholders
Project sponsor
Which elements of the project management plan isare typically the most helpful for managing project integration?
The lessons learned register
The communications management plan
The quality management plan
The scope, cost, and schedule baselines
When it comes to directing and managing the work on a project, which of the following is most useful for assigning tasks and communicating due dates and status updates?
Project management software
Work performance data
Approved change requests
Change control tools
Which of the following should be updated as part of the effort to manage project knowledge?
Issue log
Work performance information
Lessons learned register
Environmental factors
If your organization has a strong background in knowledge management through previous projects, then what should your first step be to address any knowledge gaps in your current project?
See if there is any knowledge that can be reused
Start collecting new knowledge
Share any knowledge you currently have
Discard the current knowledge you have
Which of the following techniques is most useful for predicting future performance of the team?
Variance analysis
Expert judgment
Trend analysis
Meetings
You are a project manager on a project designing a motorized toy car for children. The project team finds that a few cars can only go two miles per hour, not three miles per hour. One of the requirements for the toy car is that it must go three miles per hour. What type of change request should you initiate?
Preventive action
Corrective action
Defect repair
Updates
Why is it important to hold project retrospectives after completing a project?
A They provide an opportunity to close all commitments, agreements, contracts, and financial obligations.
B They provide an opportunity for the project team to discuss and record the lessons learned during the project.
C They give the project team one last opportunity to fix any mistakes that might still be found in the project deliverable.
D They allow the project manager to formally transfer ownership of the project deliverable to the client or stakeholders.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock