Question: 1. With reference to the table below, listing the activities of a project: Activity Duration (days) Preceding Activities A 3 - B 2 - C

1. With reference to the table below, listing the activities of a project:

Activity Duration (days) Preceding Activities
A 3 -
B 2 -
C 5 A
D 3 B
E 6 D
F 4 C,D

Draw the Activity-on-Node network diagram, including the Early Start, Early Finish, Late Start, Late Finish, Free Slack and Total Slack for each activity.

Identify the activities that are on the critical path , and the duration of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!