Question: 1. With reference to the table below, listing the activities of a project: Activity Duration (days) Preceding Activities A 3 - B 2 - C
1. With reference to the table below, listing the activities of a project:
| Activity | Duration (days) | Preceding Activities |
| A | 3 | - |
| B | 2 | - |
| C | 5 | A |
| D | 3 | B |
| E | 6 | D |
| F | 4 | C,D |
Draw the Activity-on-Node network diagram, including the Early Start, Early Finish, Late Start, Late Finish, Free Slack and Total Slack for each activity.
Identify the activities that are on the critical path , and the duration of the project.