Question: 10 Degrees, heelp Given the activities whose sequence is described by the following table Activity Immediate Predecessor(s) Time estimates (in days) Optimistic Most likely Pessimistic

10 Degrees, heelp Given the activities whose

10 Degrees, heelp

Given the activities whose sequence is described by the following table Activity Immediate Predecessor(s) Time estimates (in days) Optimistic Most likely Pessimistic m b A 3 6 8 B 2 4 4 1 ITU 1 6 2. 7 D 3 8 6 14 E 4 F 10 2. G 4 BD A, E A, E F G H1 H NO-M9N 6 9 1 J 11 16 8 12 20 10 K 2 ) .Determine the e pected corrpletion tirre and variance for each activity Activity Expected completion time, le Variance, Vit) B E H eurs