Question: Given the activities whose sequence is described by the following table: Using the appropriate PERT diagram: 1 . Calculate the expected time for Activity D
Given the activities whose sequence is described by the following table: 
Using the appropriate PERT diagram:
1 . Calculate the expected time for Activity D
2. What is the EF time for Activity F
3. What is the LS time for Activity D
4. Identify the critical path.
5. What is the expected project duration.
6. What is the probability that the project will be completed in 25 days or less?
| A. | 0.26464 |
| B. | 7 days |
| C. | 7 days |
| D. | 26 days |
| E. | B-D-E-G |
| F. | 12 days |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts