Question: (10 points) Using the data, determine the: Expected activity completion times and variance of each individual activity, and, Expected project completion time and the variance

- (10 points) Using the data, determine the:
- Expected activity completion times and variance of each individual activity, and,
- Expected project completion time and the variance of the project completion time.
Immediate Predecessor Activity B Optimistic 5 8 6 TIME IN DAYS Most Likely 6 8 8 12 6 6 3 4 7 Pessimistic 7 11 11 15 9 7 7 5 8 D F B H EGI 5 2 4 5 H End
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
