Question: (10 points) Using the data, determine the: Expected activity completion times and variance of each individual activity, and, Expected project completion time and the variance

(10 points) Using the data, determine the:

  1. (10 points) Using the data, determine the:
    1. Expected activity completion times and variance of each individual activity, and,
    2. Expected project completion time and the variance of the project completion time.

Immediate Predecessor Activity B Optimistic 5 8 6 TIME IN DAYS Most Likely 6 8 8 12 6 6 3 4 7 Pessimistic 7 11 11 15 9 7 7 5 8 D F B H EGI 5 2 4 5 H End