Question: 11. A project with planned cost and Activity schedule is shown below. Activity Planned Start Planned Finish Budget Cost G 0 4 4800 H 2

 11. A project with planned cost and Activity schedule is shown

11. A project with planned cost and Activity schedule is shown below. Activity Planned Start Planned Finish Budget Cost G 0 4 4800 H 2 8 12000 I 4 13 18000 J 7 12 10500 K 12 14 18900 L 13 18 15500 Note that start and finish times stated are from network calculation methods with the project start at 0 using the network calculation method of the textbook