Question: (11) Activity D cannot start immediately after activity A. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path

(11) Activity D cannot start immediately after activity A. The delay is expected to be 7 days. Determine by stating the possible problem, Critical Path and Project Duration to complete the process. [8 marks] Table Q1 (a) Activity Process Predecessor Duration (Days) 2 A B 3 2 4 D F G H I J K L M Wafer Processing Dry etching Wet etching Plasma aching Thermal treatment Chemical vapor deposition Electrochemical deposition Wafer testing Die preparation IC bonding IC plating IC testing IC packaging A B A DBC C F EF G H I K JL 1 3 4 2 3 2 1