Question: #11 Can someone help solve this problem? 1 Book Ask ferences Problem 2-5 (Algo) An operation has a scrap rate of 15%. As a result,

#11 Can someone help solve this problem?
#11 Can someone help solve this problem? 1 Book
1 Book Ask ferences Problem 2-5 (Algo) An operation has a scrap rate of 15%. As a result, 85 sellable pieces per hour are produced. a. How many pieces per hour are produced, including scrap? (Enter your answer as a whole number.) I pieces b. What is the potential increase in labor productivity that could be achieved by eliminating the scrap? (Enter your answer as a percentage rounded to one decimal.) The potential increase in labor productivity %