Question: 11. Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks: Activity Optimistic Time (weeks) Most

11. Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks:

Activity

Optimistic Time (weeks)

Most Likely Time (weeks)

Pessimistic Time (weeks)

A

8 10 12

B

4 10 16

C

4 5 6

D

6 8 10

E

4 7 12

F

6 7 9

G

4 8 12

H

3 3 3

The critical path is A-B-D-G-H.

(Round your answers to 4 decimal places, e.g. 1.7582.)

(a) Calculate the probability of completing the project in 35 weeks.

P(project 35) =

(b) Calculate the probability of completing the project in 44 weeks.

P(project 44) =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!