Question: Using the information provided in the table, the network diagram and the expected project completion time -39 weeks: Network diagram The critical path is A-B-D-G-H.

 Using the information provided in the table, the network diagram and

Using the information provided in the table, the network diagram and the expected project completion time -39 weeks: Network diagram The critical path is A-B-D-G-H. (Round your answers to 4 decimal places, e.g. 1.7582.) (a) Calculate the probability of completing the project in 35 weeks. P(project 35) - (b) Calculate the probability of completing the project in 43 weeks. P(project 43)