Question: Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks: Activity Optimistic Time (weeks) Most Likely
Using the information provided in the table, the network diagram and the expected project completion time = 39 weeks:
| Activity | Optimistic Time (weeks) | Most Likely Time (weeks) | Pessimistic Time (weeks) | |||
|---|---|---|---|---|---|---|
| A | 8 | 10 | 12 | |||
| B | 4 | 10 | 16 | |||
| C | 4 | 5 | 6 | |||
| D | 6 | 8 | 10 | |||
| E | 4 | 7 | 12 | |||
| F | 6 | 7 | 9 | |||
| G | 4 | 8 | 12 | |||
| H | 3 | 3 | 3 |
The critical path is A-B-D-G-H.
(Round your answers to 4 decimal places, e.g. 1.7582.)
(a) Calculate the probability of completing the project in 34 weeks.
P(project 34) =
(b) Calculate the probability of completing the project in 41 weeks.
P(project 41) =
please explain your steps
Step by Step Solution
There are 3 Steps involved in it