Question: 11.1 Develop a budget for the project described in Table 11.11 assuming that the cost of each activity is linearly distributed over its duration.
11.1 Develop a budget for the project described in Table 11.11 assuming that the cost of each activity is linearly distributed over its duration. TABLE 11.11 Activity Duration Immediate Cost (days) predecessors A 3 $3,000 B 4 - 2,000 C 3 - 6,000 D 2 2.000 E 1 B 1,000 F 5 A 10,000 G 2 B 4,000 H 3 B 9.000 11 C 11,000 J 3 D. E 3,000 K 1 FG 1,000 JM L 4 K 2.000 M 4 J. H 8.000 a. Assume an early-start schedule. b. Assume a late-start schedule. c. Assume that a "leveled budget is desired (i.e., the same daily cost is desired for each day of the project).
Step by Step Solution
There are 3 Steps involved in it
To develop a budget for the project well calculate the daily costs of each activity considering both earlystart and latestart schedules Additionally w... View full answer
Get step-by-step solutions from verified subject matter experts