Question: 11.1 Develop a budget for the project described in Table 11.11 assuming that the cost of each activity is linearly distributed over its duration. TABLE
11.1 Develop a budget for the project described in Table 11.11 assuming that the cost of each activity is linearly distributed over its duration.
TABLE 11.11
| Activity | Duration (days) | Immediate predecessors | Cost |
|---|---|---|---|
| A | 3 | $3,000 | |
| B | 4 | 2,000 | |
| C | 3 | 6,000 | |
| D | 2 | C | 2,000 |
| E | 1 | B | 1,000 |
| F | 5 | A | 10,000 |
| G | 2 | B | 4,000 |
| H | 3 | B | 9,000 |
| I | 11 | C | 11,000 |
| J | 3 | D, E | 3,000 |
| K | 1 | F, G | 1,000 |
| L | 4 | K | 2,000 |
| M | 4 | J, H | 8,000 |
-
Assume an early-start schedule.
-
Assume a late-start schedule.