Develop a budget for the project described in Table 11 assuming that the cost of each activity
Question:
Develop a budget for the project described in Table 11 assuming that the cost of each activity is linearly distributed over its duration.
a. Assume an early-start schedule.
b. Assume a late-start schedule.
c. Assume that a “leveled budget” is desired (i.e., the same daily cost is desired for each day of the project).