Question: 11.1 Develop a budget for the project described in Table 11.11 assuming that the cost of each activity is linearly distributed over its duration. TABLE
-
11.1 Develop a budget for the project described in Table 11.11 assuming that the cost of each activity is linearly distributed over its duration.
TABLE 11.11
Activity Duration (days) Immediate predecessors Cost A 3 $3,000 B 4 2,000 C 3 6,000 D 2 C 2,000 E 1 B 1,000 F 5 A 10,000 G 2 B 4,000 H 3 B 9,000 I 11 C 11,000 J 3 D, E 3,000 K 1 F, G 1,000 L 4 K 2,000 M 4 J, H 8,000 -
Assume an early-start schedule.
-
Assume a late-start schedule.
-
Assume that a leveled budget is desired (i.e., the same daily cost is desired for each day of the project).
-