Question: 17. The forward pass in a network calculation determines: a. The critical path of the project. b. The earliest times activities can begin. c. The

17.

The forward pass in a network calculation determines:

a.

The critical path of the project.

b.

The earliest times activities can begin.

c.

The latest times activities can be finished.

d.

The total slack time available.