Question: 18. For a project in which the projects scope exceeds the projects allocated budget, a close examination of the WBS reveals that the scope can
18. For a project in which the projects scope exceeds the projects allocated budget, a close examination of the WBS reveals that the scope can be reduced without adversely affecting the deliverables value at delivery to the user.
What are two possible causes that would just such a conclusion
Choose 2 answers
The users asked for more scope than what was required to meet business need.
The scope variance would be reset to zero, and the schedule variance would become favorable
Collected requirements were not evaluated for causing or adding value to the deliverable
Fast tracking the schedule would reduce the risk that inspections will be required
Crashing the projects scope reduced the value of conformance work