Question: 18. For a project in which the projects scope exceeds the projects allocated budget, a close examination of the WBS reveals that the scope can

18. For a project in which the projects scope exceeds the projects allocated budget, a close examination of the WBS reveals that the scope can be reduced without adversely affecting the deliverables value at delivery to the user.

What are two possible causes that would just such a conclusion

Choose 2 answers

The users asked for more scope than what was required to meet business need.

The scope variance would be reset to zero, and the schedule variance would become favorable

Collected requirements were not evaluated for causing or adding value to the deliverable

Fast tracking the schedule would reduce the risk that inspections will be required

Crashing the projects scope reduced the value of conformance work

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!