Question: 18) The planning for a project determined it is composed of the following tasks, predecessors, and durations (note the two columns): TASK PREDECESSORS DURATION TASK

18) The planning for a project determined it is composed of the following tasks, predecessors, and durations (note the two columns):

TASK

PREDECESSORS

DURATION

TASK

PREDECESSORS

DURATION

A

-

6

N

K

9

B

-

7

O

L

5

C

B

5

P

O

7

D

A,C

10

Q

M

20

E

D,I

16

R

M

10

F

-

9

S

R

12

G

F

11

T

R

10

H

-

10

U

N,P,T

8

I

G,H

18

V

U

9

J

E

8

W

Q,S,V

10

K

E

5

X

Q,S

6

L

E

8

Y

X

9

M

J

8

Z

Q

5

Without using any software package, manually construct the appropriate CPM network diagram using the activity on arrow convention and the techniques discussed in the class. You must submit your diagram for full credit:

In an attached file, address the following:

(a) For each task, give the Earliest Start, Latest Start, Earliest Finish, Latest Finish, and Total Float.

18) The planning for a project determined it is composed of the

(b) What sequence of tasks makes up the Critical Path? Include any dummy activities that may be a part of the critical path.

(c) What is the total duration of the project as planned?

Sequence of tasks that make up the critical path: Total duration of the project as planned

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!