Question: 1)Find the project expected completion time. (6 points) * 25 30 29 23 2)The ES & EF times of activity E are: (4 points) *

1)Find the project expected completion time. (6 points) * 25 30 29 23
2)The ES & EF times of activity E are: (4 points) * 6 & 12 6 & 10 9 & 19 6 & 15
3)The LS & LF times of activity C are (4 points) * 5 & 9 None of the above 2 & 6 9 & 13
4)The slack of activity E is: (4 points) * 7 5 None of the above 8
5)Activity C can be delayed by: (4 points) * 3 None of the above 2 0
6)Activity B can be delayed by: (4 points) * 2 None of the above 4 1
7)The CP is: (4 points) * A, C, E, F NONE of the above A, B, D, F A, C, D, F
The table below shows the information related to a project that involves the merger of two marketing firms (in days). Predecessor(s) Time Activity 2 B 7 A A B,C D, E D E F 4 10 6 11Step by Step Solution