Question: Activity Preceding Time A ----------- 8 B ----------- 3 C A 7 D A,B 3 E C 4 F D 6 Find the project expected
| Activity | Preceding | Time |
| A | ----------- | 8 |
| B | ----------- | 3 |
| C | A | 7 |
| D | A,B | 3 |
| E | C | 4 |
| F | D | 6 |
Find the project expected completion time.
17
18
19
16
Calculate ES & EF times of activity F.
9 and 16
8 and 14
10 and 16
11 and 17
The LS & LF times of activity E.
14 and 18
15 and 19
13 and 17
12 and 16
The slack of activity D is:
5
3
2
4
Activity C can be delayed by:
2
1
3
0
Activity B can be delayed by:
7
5
6
4
The CP is
A, D, F
A, C, E
NONE
B, D, F