Question: Activity Preceding Time A ----------- 8 B ----------- 3 C A 7 D A,B 3 E C 4 F D 6 Find the project expected

Activity

Preceding

Time

A

-----------

8

B

-----------

3

C

A

7

D

A,B

3

E

C

4

F

D

6

Find the project expected completion time.

17

18

19

16

Calculate ES & EF times of activity F.

9 and 16

8 and 14

10 and 16

11 and 17

The LS & LF times of activity E.

14 and 18

15 and 19

13 and 17

12 and 16

The slack of activity D is:

5

3

2

4

Activity C can be delayed by:

2

1

3

0

Activity B can be delayed by:

7

5

6

4

The CP is

A, D, F

A, C, E

NONE

B, D, F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!